Precinct 4 Closed Bridges and Bridge Construction Update

November 16th, 2009
 

Freeman Road @ Trib to Hickory Creek

• Under Construction

North Freeman Bridge was awarded to Atascosa Bridge Company. There are 135 working days in the schedule with a start date of August 26th, 2009. The standard work week is M-F and any rain/weather delays will be added back into the schedule.



 George Owens Road @ Wolf Branch
Closed by TxDOT inspectors due to steel pilings and deck safety issues
Part of new OD NEAL BRINSAP Agreement – letting date TBD

Currently in design phase by TxDOT - approx. 30% complete


Old Stoney Road @ Tributary to Denton Creek
Closed by TxDOT inspectors due to deck and foundation safety issues – Has Bypass
Part of new OD NEAL BRINSAP Agreement – letting date TBD

County added to Smith Schluter Old Stoney Project to speed up replacement – Completion Date TBD


South County Line Road Bridge
Under Construction
Contractor is 2L Construction Company. They closed the road on November 9th and are scheduled to open the bridge to traffic on December 21st, 2009 – if the weather permits them to work according to the planned schedule. The new bridge will be constructed of precast box culverts and the driving surface will 24 feet wide – 12 foot lanes.

 

All project schedules are subject to change due to weather / rain delays.

 

If you have any questions about these bridges or any others in Precinct 4 please call Robin Davis, Project Coordinator at 940.349.2963 or via E-mail.  Your comments and concerns are very important to us and we are always here to help.